Construction Work Order Template

On a construction site the work order is usually the extra-work ticket: the numbered record of what got directed in the field, who did it, and what it consumed, so the change order has something behind it besides a conversation. The form below is loaded with a typical directed change — swap in your site, scope, and crew, then download the PDF for the daily file.

A sample construction job is preloaded below — edit every field, then download the PDF. Free, no signup.

Work order
WO number (auto)
Priority
Date issued
Date needed
Date completed
Company
Company name
Phone
Email
Address
People & location
Requested by
Requester contact
Assigned to
Assignee contact
Location
Asset / equipment
Description of work
Parts & materials
$495.00
$296.00
$210.00
$95.00
Labor
$312.00
$552.00
$425.00
$142.50
Tax, notes & sign-off
Tax rate %
Notes
Company Name
WORK ORDER
WO-1001
Date issued
Aug 22, 2026
Date needed
Priority
High
Date completed
Requested by
Assigned to
Location
Northgate Commerce Center — Building 1, grid C4–C6 slab
Asset / Equipment
Slab on grade, floor drain relocation (2 drains)
Description of work

Extra work directed by owner's rep at site walk: relocate two floor drains in the slab area of grid C4-C6 to clear the revised equipment layout. Saw-cut and remove existing slab section, excavate, cut and re-tie drain lines to new locations, form and pour back to match, verify slope to spec, patch and broom finish. Concrete sub performed the pour-back; plumbing sub performed the re-tie. Owner's rep witnessed slope check and signed at close.

Parts & Materials
PART / MATERIAL
QTY
UNIT COST
TOTAL
Ready-mix concrete, 4000 psi (cu yd)
3
$165.00
$495.00
Drain body, trap and PVC fittings
2
$148.00
$296.00
Rebar dowels, epoxy, form lumber
1
$210.00
$210.00
Saw blade wear, disposal of slab spoils
1
$95.00
$95.00
Parts total
$1,096.00
Labor
LABOR / TASK
HOURS
RATE
TOTAL
Layout, saw-cut and demo slab section (2-person)
4
$78.00
$312.00
Excavate, re-tie drain lines (plumbing sub)
6
$92.00
$552.00
Form, dowel, pour back and finish (concrete sub)
5
$85.00
$425.00
Superintendent supervision and slope verification
1.5
$95.00
$142.50
Labor total
$1,431.50
TOTAL$2,527.50
Notes

Work directed verbally by owner's rep at the 7:15 site walk; this order is the written record of that direction and is submitted as backup to change order request COR-014. Slope verified at 1/8 in. per ft and witnessed. Excludes any finish flooring work over the patched area. Rebar dowel spacing per structural detail S-4.2.

Authorized by (signature)
Print name
Date
Created with work-order-template.comPage 1 of 1
WO-1001
$2,527.50

The extra-work ticket: what a construction work order is actually for

Most construction work orders are not the base contract work — that runs on the schedule of values and the daily report. The work order is what you write when someone in the field directs something that isn't in the drawings: a relocation, a repair to another trade's damage, an unforeseen condition, a client's on-the-spot addition. Write it the same day, number it, and name who gave the direction. A ticket written a week later against a verbal instruction is worth a fraction of one written while the superintendent is still standing there.

The single most useful line on the form is the one that says who authorized it and when. Verbal direction is normal on a jobsite and it is not the problem; the problem is verbal direction with no written trace. Put the name, the time, and the exact words as close as you can recall them into the description, and the ticket becomes the document a change order request is built on rather than a memory to argue about at closeout.

Subcontractors, crew hours, and force-account backup

Extra work is usually billed on force account — actual time and materials, documented — so the labor lines have to be defensible line by line. Break the hours out by crew and by sub rather than presenting one blended number: the demo crew, the plumbing sub's re-tie, the concrete sub's pour-back, and supervision each read as separate work with separate rates, which is exactly how an owner's rep or a CM will review it. This template's labor table is sized for that split.

Log materials that were actually consumed on the extra work, not what was on the truck: concrete by the yard, fittings by the piece, and the consumables that get quietly absorbed otherwise — blade wear, form lumber, epoxy, and disposal of what came out. Equipment time belongs here too if a machine was mobilized for the extra scope. Every one of those lines is a real cost, and the ones nobody writes down are the ones that come out of the general contractor's margin.

From field ticket to change order, and what to exclude

The paper trail on a construction job runs direction → work order → change order request → executed change order → payment application, and the work order is the only one of those written while the work is happening. Reference the COR number on the ticket once one exists so the two documents point at each other. Get a signature at the close of the shift — an owner's rep, CM, or architect's field representative signing the ticket is not agreement on price, and it should not pretend to be; it is agreement that the work described was performed and the hours shown were spent.

State exclusions plainly. Directed work almost always stops short of the finishes, the testing, or the coordination someone assumes is included, and one line naming what this ticket does not cover prevents a second argument later. On a project where change orders run through a formal review, that sentence is often the difference between a ticket that gets approved as written and one that gets sent back.

Construction work order FAQ

What is a construction work order used for?

Almost always extra work: something directed in the field that isn't in the contract drawings — a relocation, unforeseen condition, damage repair, or an owner addition. It records what was directed, who directed it, and the crew hours and materials it consumed, and it becomes the backup for a change order request.

Is a construction work order the same as a change order?

No. The work order is the field ticket written while the work happens; the change order is the executed contract amendment that adjusts price and time. The ticket is the evidence, the change order is the agreement. Reference the change order request number on the ticket once one exists so the two documents point at each other.

How should subcontractor hours be shown on a construction work order?

Broken out by sub and by crew with their own rates, never blended into one number. Force-account work is reviewed line by line, so a ticket showing demo crew, plumbing sub, concrete sub, and supervision separately is far easier to approve than a single lump of hours.

Does signing a field work order mean the owner agreed to the price?

No, and the ticket should not imply it does. A signature from an owner's rep or CM confirms the described work was performed and the hours shown were spent. Price is settled in the change order. Saying so on the form keeps signatures easy to get.